Reading time: 2 minutesThe maintenance concept primarily covers the analyses and upgrade concepts already submitted to the Federal Nuclear Safety Inspectorate (ENSI). Maintenance of Mühleberg nuclear power plant has been an ongoing task for BKW since the facility first went into operation, and maintenance work has been planned and carried out at the plant at regular intervals throughout its years of operation. As part of the latest regular safety check in 2010 (PSÜ2010), ENSI submitted a report on the plant's long-term operation along with an appropriate maintenance concept.
The maintenance concept which has now been submitted to DETEC covers the following aspects: PSÜ2010 report on longterm operation Maintenance concept for the core mantle Concept for upgrading a diversionary heat sink (Saanental ground water catchment, elevated reservoir etc.) Concept for upgrading an alternative fuel pool cooling system, an additional residual heat removal system and fault proof fuel pool instrumentation Earthquake safety concept including maintenance work on the Mühleberg hydroelectric power plant dam.
By submitting the concept, BKW is meeting the requirements stipulated by the Federal Administrative Court. All the required documents for BKW's application for the further operation of Mühleberg nuclear power plant beyond 28 June 2013 are therefore now in the hands of the authorities.
BKW expects the cost of the planned upgrade measures to amount to around CHF 170 million. Added to this are the maintenance and replacement costs of around CHF 20 million per year for the next ten years.
Media Contact:
BKW FMB Energie AG Viktoriaplatz 2 3000 Bern 25 Telefon 031 330 51 11 Telefax 031 330 56 35
Editor's note: Image rights belong to the respective publisher.
Source: BKW FMB Energie AG, Press release